Wednesday, July 31, 2013

31st July 2013

All tiles have now been laid in the master ensuite, main bathroom, W.C and laundry. They looked a little darker than what I thought they would be, but I think they will look good. I might end up changing the wall colour in these areas, but will wait to see the finished product. All that is left to do is grouting and a good clean. The tiler also put in the laundry tub this afternoon. Its very ugly though, but will do for now. After handover we are going to install our own laundry cupboards as the thought of spending $1,000 per metre for laundry cubpards with MJH was a bit of a joke really. We worked out we could do it much cheaper ourselves like most things.

The Electricians were also on site today. All powerpoints and light switches have now been cut out along with holes they have drilled in the ceiling for the baton fixes. It seemed like all the holes had been cut in the right places, but we didn't have the electrical plan on us at the time, so will take it back tomorrow to make sure. There were only 2 holes that didn't seem to be right.

The gyprockers had also been back to fix up gyprock joins or areas that needed to be redone after last weeks first coat of paint. I'd say they will be back tomorrow to sand these areas, so the painters can come back and do the second coat. Our SS left a message on my phone today to say that the painters should be finished by middle of next week.

We are still not happy with the facade colour. We think it still needs a bit more warmth, more like the colour of the brick mortar. It looks a lot lighter than the inside walls, which just isnt right considering its the same colour. We think the painter must have mixed the paint in with the concrete or something...anyway. We will fix that after handover.

 
Master Ensuite

 
Master Ensuite

 
Master Ensuite

 
Master Ensuite

 
Laundry

 
W.C

 
Main Bathroom

 
Main Bathroom

 
Main Bathroom

 
Laundry

 
Door Frames + Doors Painted

 
Powerpoint Cutouts - Activity Room (Desk)

 
Powerpoint Cutouts - Kitchen

 
Powerpoint Cutouts - Living Area

 
Light Switch Cutouts - Activity Area + Hall

 
Powerpoint Cutout + Gyprock Patching in Bedroom 2

 
Facade with no sun on it

 
Facade with no sun on it
 
Facade with no sun on it