Timeline

2014



05 Aug 2014 - Lights installed

23 Jul 2014 - Final Occupation Certificate received

22 Jul 2014 - Sent copy of driveway approval to private certifier

22 Jul 2014 - Driveway approved by Council

18 Jul 2014 - Driveway sealed

18 Jul 2014 - Brickwork and some patching (maintenance)

14 Jul 2014 - Driveway expansion joint cuts

11 Jul 2014 - Painting fixes (maintenance)

09 Jul 2014 - Driveway poured


08 Jul 2014 - Crack fixes (maintenance)

07 Jul 2014 - Driveway formwork erected


03 Jun 2014 - Kitchen benchtop repair / polish (maintenance)

22 May 2014 - Sliding doors alignment adjustment (maintenance)

22 May 2014 - Electrical work (maintenance)

03 Apr 2014 - 3 month post build review inspection



31 Jan 2014 - 3 month post build maintenance requirements sent to MJH


2013

25 Sep 2013 - Delivery of media room lounge

25 Sep 2013 - Service + Warranty Information sent from MJH

23 Sep 2013 - Plumbers back to fix leaking bathroom taps

06 Sep 2013 - PCI fix ups - electrical, shower screen

06 Sep 2013 - Delivery of bed, sofa, appliances

06 Sep 2013 - Carpet installed

05 Sep 2013 - PCI fix ups - electrical, bricks and a few minor issues

05 Sep 2013 - Skirting boards installed

04 Sep 2013 - Floorboards installed

04 Sep 2013 - Hot water system + kitchen appliances installed

04 Sep 2013 - PCI fix ups

03 Sep 2013 - Handover

03 Sep 2013 - Hot water system + kitchen appliances delivered

02 Sep 2013 - Painters back for touch ups

28 Aug 2013 - Interim Occupation Certificate issued

28 Aug 2013 - Home + Contents Insurance organised

28 Aug 2013 - Requested valuation from Rams

28 Aug 2013 - Final Progress Payment Request

27 Aug 2013 - Private Certifier Inspection

27 Aug 2013 - PCI Walkthrough

26 Aug 2013 - Kitchen splashback installed

26 Aug 2013 - Sliding door inserts installed

23 Aug 2013 - Data box in garage installed

22 Aug 2013 - MJH inspection + plastering touch ups

21 Aug 2013 - Final Occupation Certificate Inspection

20 Aug 2013 - Removal of security fencing

16 Aug 2013 - Finishing off of silicon and grout in wet areas

15 Aug 2013 - Clean up including removal of film from windows and sliding doors

13 Aug 2013 - Shower screens, bathroom mirrors and study nook data points installed

10 Aug 2013 - Door Handles, towel rails and toilet roll holders installed

07 Aug 2013 - Front yard clean up

07 Aug 2013 - Bath installed

07 Aug 2013 - All tapware / shower rails installed

07 Aug 2013 - Gas bayonet and data points fitted

07 Aug 2013 - Shelving / rails for closets, wardrobes, pantry etc

07 Aug 2013 - Plumbing

06 Aug 2013 - Painting finished

06 Aug 2013 - All benchtops installed

06 Aug 2013 - Powerpoints, light switches + baton fixes installed

03 Aug 2013 - Kitchen measured for splashback

03 Aug 2013 - Desk installed

02 Aug 2013 - Alarm installed

31 July 2013 - Progress Payment # 5 Request

31 July 2013 - Gyprock patching

31 July 2013 - Electrical cutouts - powerpoints + light switches

31 July 2013 - Tiling + laundry tub installed

29 July 2013 - Tiling started

26 July 2013 - Facade bag + paint and more painting

25 July 2013 - Electrical cut outs started

25 July 2013 - Front door + facade stained

25 July 2013 - Painting of doors

24 July 2013 - Painting started

23 July 2013 - Floor joins to wet areas

23 July 2013 - Shelving and desk frame in Activity Area

23 July 2013 - Kitchen installed and bathroom cupboards assembled including handles

22 July 2013 - Kitchen delivered

19 July 2013 - Carpentry

18 July 2013 - Carpentry

17 July 2013 - Garage door delivered and installed

17 July 2013 - Waterproofing

16 July 2013 - Variation #021 recieved - skirting boards to be left uncut and unpainted

16 July 2013 - Sanding of the plaster (day 2)

15 July 2013 - Water tank plumbing

15 July 2013 - Sanding of the plaster

14 July 2013 - Downpipes installed

12 July 2013 - Shower recess boxes put in

12 July 2013 - Cornices put up

10 July 2013 - Water tank delivered

10 July 2013 - Gyprocking finished

08 July 2013 - Plastering started

06 July 2013 - Timber frame and caps for columns put in

05 July 2013 - Gyprocking started

04 July 2013 - Variation #020 recieved - move 2 x powerpoints + add 2 x data points

04 July 2013 - Progress Payment # 4 Request

04 July 2013 - Gyprock delivered

04 July 2013 - Insulation put in

04 July 2013 - Electrical walk through with SS

02 July 2013 - Data cables put in

01 July 2013 - Electrical cables, powerpoints and light switch points put in

29 June 2013 - Bricks cleaned

27 June 2013 - Eaves started

26 June 2013 - Eaves + timber for front facade delivered

17 June 2013 - Brickwork started

14 June 2013 - Sand delivered for brickwork and dump bin delivered

13 June 2013 - Bricks delivered, plumbing rough in and roof scaffolding taken down

11 June 2013 - Colourbond roof finished

10 June 2013 - Roof battens put up in preparation for roof

07 June 2013 - Roof scaffolding put up in preparation for roof

06 June 2013 - Fascias and guttering put up and colourbond roof delivered

05 June 2013 - Progress Payment # 3 Request

05 June 2013 - Guttering delivered

04 June 2013 - Windows and door frames put in

04 June 2013 - Roof frame complete

31 May 2013 - Variation #019 recieved - credit for extra piering

31 May 2013 - Variation #018 recieved - credit for concrete piers

30 May 2013 - Erection of frame commenced

29 May 2013 - Frame delivered

28 May 2013 - Site leveled and termite barrier laid

22 May 2013 - Progress Payment # 2 Request

18 May 2013 - Slab poured

16 May 2013 - Rest of formwork laid

15 May 2013 - Waffle pods laid including mesh

14 May 2013 - Formwork, piering and delivery of waffle pods

07 May 2013 - Plumbing

02 May 2013 - Site cut

30 April 2013 - All orders placed and file sent to Supervisor to arrange for site cut

22 April 2013 - Put on Construction List

22 April 2013 - Authority to Commence Construction Letter recieved

22 April 2013 - Variation #015 recieved - tender review extension

22 April 2013 - Variation #011 recieved - development approval

16 April 2013 - Home Loan Settlement recieved

08 April 2013 - Home Loan Unconditional Approval recieved

01 March 2013 - Variation #012 received - tender review extension

31 January 2013 - Variation #010 recieved - electrical selections

29 January 2013 - Final Electrical Selections submitted

23 January 2013 - Progress Payment # 1 Request
23 January 2013 - Submission to Rams for Construction Loan Approval
22 January 2013 - CDC Approval
18 January 2013 - Electrical Appointment with MJH
2012
21 Dec 2012 - Electrical Appointment Letter + Electrical Information recieved
20 Dec 2012 - Plans submitted to CDC
20 Dec 2012 - Developer Approval recieved
20 Dec 2012 - Landscape Plan V#4 submitted
20 Dec 2012 - Changes requested to Landscape Plan by Developer
17 Dec 2012 - Landscape Plan V#3 submitted
13 Dec 2012 - Changes requested to Landscape Plan by Developer
05 Dec 2012 - Letter re delays experienced recieved from MJH to forward to Office of State Revenue
04 Dec 2012 - Request to extend Home Builders Bonus due to delays experienced
22 Nov 2012 - Variation #009 recieved - Provisional allowance for 9.0 extra lineal metres
16 Nov 2012 - Amended Plans recieved
03 Oct 2012 - Site Plan fail due to sewer line
03 Oct 2012 - Variation #008 recieved - Facade changes
02 Oct 2012 - Home Owners Warranty Certificate (HOW) recieved
26 Sep 2012 - Variation #006 recieved - Sydney Water
19 Sep 2012 - Landscape Plan V#2 submitted
19 Sep 2012 - Changes requested to Landscape Plan by Developer
14 Sep 2012 - Landscape Plan V#1 submitted
16 Aug 2012 - HIA Contract Signed
01 Aug 2012 - Contract Issued
31 Jul 2012 - Building Contract, Plans + Contract Signing Checklist recieved
25 Jul 2012 - Variation #003 recieved - Air con, wall opening fix, 3 phase power, tap + reduction
13 Jul 2012 - Colour sign off recieved + File with Estimating Department
12 Jul 2012 - Appointment with MJH to sign off on plans
10 Jul 2012 - Preliminary Plans + Pre Contract Variation #001 recieved - Depth of dwelling reduced
09 Jul 2012 - Colour selection changes recieved
09 Jul 2012 - Colour Selection Appointment with MJH
20 Jun 2012 - Land Settlement
08 Jun 2012 - Land Loan Approval recieved
05 Jun 2012 - Consolidated Tender, Soil Class Certificate + 88b Excerpt recieved
25 May 2012 - Deposit Variation signed off and submitted
01 May 2012 - First Appointment with MJH - Pre Colour Walkthrough
16 Apr 2012 - Deposit Variation #2
05 Apr 2012 - Deposit Variation #1
2011
10 Jul 2011 - Holding Fee Paid to Medallist Holdings

1 comment:

  1. INTERNATIONAL CONCEPT OF WORK FROM HOME
    Work from home theory is fast gaining popularity because of the freedom and flexibility that comes with it. Since one is not bound by fixed working hours, they can schedule their work at the time when they feel most productive and convenient to them. Women & Men benefit a lot from this concept of work since they can balance their home and work perfectly. People mostly find that in this situation, their productivity is higher and stress levels lower. Those who like isolation and a tranquil work environment also tend to prefer this way of working. Today, with the kind of communication networks available, millions of people worldwide are considering this option.

    Women & Men who want to be independent but cannot afford to leave their responsibilities at home aside will benefit a lot from this concept of work. It makes it easier to maintain a healthy balance between home and work. The family doesn't get neglected and you can get your work done too. You can thus effectively juggle home responsibilities with your career. Working from home is definitely a viable option but it also needs a lot of hard work and discipline. You have to make a time schedule for yourself and stick to it. There will be a time frame of course for any job you take up and you have to fulfill that project within that time frame.

    There are many things that can be done working from home. A few of them is listed below that will give you a general idea about the benefits of this concept.

    Baby-sitting
    This is the most common and highly preferred job that Women & Men like doing. Since in today's competitive world both the parents have to work they need a secure place to leave behind their children who will take care of them and parents can also relax without being worried all the time. In this job you don't require any degree or qualifications. You only have to know how to take care of children. Parents are happy to pay handsome salary and you can also earn a lot without putting too much of an effort.

    Nursery
    For those who have a garden or an open space at your disposal and are also interested in gardening can go for this method of earning money. If given proper time and efforts nursery business can flourish very well and you will earn handsomely. But just as all jobs establishing it will be a bit difficult but the end results are outstanding.

    Freelance
    Freelance can be in different wings. Either you can be a freelance reporter or a freelance photographer. You can also do designing or be in the advertising field doing project on your own. Being independent and working independently will depend on your field of work and the availability of its worth in the market. If you like doing jewellery designing you can do that at home totally independently. You can also work on freelancing as a marketing executive working from home. Wanna know more, email us on workfromhome.otr214423@gmail.com and we will send you information on how you can actually work as a marketing freelancer.


    Internet related work
    This is a very vast field and here sky is the limit. All you need is a computer and Internet facility. Whatever field you are into work at home is perfect match in the software field. You can match your time according to your convenience and complete whatever projects you get. To learn more about how to work from home, contact us today on workfromhome.otr214423@gmail.comand our team will get you started on some excellent work from home projects.


    Diet food
    Since now a days Women & Men are more conscious of the food that they eat hence they prefer to have homemade low cal food and if you can start supplying low cal food to various offices then it will be a very good source of income and not too much of efforts. You can hire a few ladies who will help you out and this can be a good business.

    Thus think over this concept and go ahead.

    ReplyDelete