10th July 2014

Yesterday was very exciting. Our driveway and crossover were poured. We are really happy with it so far. The guys from Fogolin & Sons did such a neat job and they were such lovely guys. They will be back tomorrow afternoon to cut it and then back next Thursday to seal it. So by next weekend we will finally be able to use it.

It has made such a difference to the front of the house. It really sets it off. All we need to do now is all the landscaping and decking to the front porch.

We ended up having 1/3 of our lights put up. We were hoping to have everything done in the one day, but the electricians were slower than expected. The electricians aren't available again for another week or so, so that is now going to have to wait.

Some pics of yesterdays work (sorry went a bit crazy with photos, but I was so excited I couldn't help myself):